You are most likely looking for 'startcredit' and 'endcredit'. Be sure to
define at least one cost account and assign it to the task. The FirstProject
in the Examples directory illustrates the use of these keywords.
Chris
On Monday 04 August 2003 07:48, Ludo.Vangilbergen@SpaceChecker.com wrote:
> Hi,
>
> I\'m taking charge of an ongoing project. Trying to dig into the various
> workpackages, I found TaskJuggler and started editing my project file. Soon
> I ran into the problem of specifying the procurement costs. That is: how
> can I specify (non manpower) costs that come with a particular workpackage
> (task), such as travel costs - buying software - hire of material to
> complete the task? The \"Features and Highlights\" do specify that \"Task
> may have initial costs, finishing costs\", but, having searched through the
> documentation and the example files, I haven\'t been able to find the right
> words in the description language to define them. Could you help me out?
>
> Thanks
>
> Ludo
>
> Name : Ludo Vangilbergen
-- KDE 3.1: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Mon Aug 04 2003 - 13:37:13 CEST