I am starting to use taskjuggler, great project.
Question:
if I have to scenarios that involver different loads for a specific
task, how can I handle that. For example, I may have an alternative
scenario that corresponds to a case were a specific tasl is needed also
bu another project and is therefore more prioritary, so I am willing to
allocate a larger portion of a given resource (myself). How can I do that.
Thanks,
Paco
-- With kind regards / Saludos cordiales Paco López Dekker paco.lopez@starlab.es, Starlab Edifici de l'Observatori Fabra, Muntanya del Tibidabo Cami de l'Observatori s/n, 08035 Barcelona Spain Phone: + 34 93 254 0365, Fax +34 93 212 6445 Cellphone: +34 699 91 88 20 ___________________________________________ Starlab, Living Science http://starlab.es This email is for the intended addressee only. If you have received it in error please return to sender and do not distribute it. -- To unsubscribe, email: taskjuggler-devel-unsubscribe@suse.com For additional commands, email: taskjuggler-devel-help@suse.com