andreas.rau@utoronto.ca wrote:
>I\'m new to TaskJuggler. Nice work.
>
>In my project I\'m more or less the only resource. Is it possible to set TaskJuggler up so that one resource can work on say two tasks on the same day instead of one task at a time? E.g. resource1 has 9 workinghours/day and he spends 6 hours on task1 (priority 1000) and 3 hours on task2 (priority 500)... something like that.
>
>Thanks.
>
>Name : Andreas
>
>
>
use limits [dailym,ax 4h } to split allocation to two tasks
HTH and I am not mistaken
mfg ET