From: Chris Schlaeger (cs_at_suse.de)
Date: Mon May 10 2004 - 11:35:21 CEST
From: Chris Schlaeger <cs@suse.de> Date: Mon, 10 May 2004 11:35:21 +0200 Message-Id: <200405101135.22726.cs@suse.de> Subject: Re: [taskjuggler-devel] *** Request via TaskJuggler Web Site ***
The version 2 xml reports have full scenario support. tjx2gantt only works
with the version 1 xml reports. We are still looking for somebody to continue
tjx2gantt development.
Chris
On Sunday 11 April 2004 03:57, blo113@psu.edu wrote:
> I am using TaskJuggler for a school project, specifically just to create
> Gantt charts. Is the scenarios feature enabled for the xmlreports need to
> generate the Gantt charts? So far, I haven\'t been able to display
> multiple scenarios on a single Gantt chart.
>
> Thanks!
>
> Name : Brianne Omatick
-- KDE 3.2: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Mon May 10 2004 - 11:35:27 CEST