[taskjuggler-devel] Re: More suggestions

From: Chris Schlaeger (cs_at_kde.org)
Date: Sun Jun 25 2006 - 12:32:46 CEST


From: Chris Schlaeger <cs@kde.org>
Message-ID: <1abb.449e664d@www.taskjuggler.org>
Date: Sun, 25 Jun 2006 12:32:46 +0200 (CEST)
Subject: [taskjuggler-devel] Re: More suggestions


The first 2 shouldn't be too difficult to do. I'll add them to the TODO list. But I'm not so sure about the 3rd one. Holidays don't have to be within the project time frame. If this doesn't work for you, then it's a bug. Task dates are strictly checked because we had several complains about falsely calculated projects due to misspelled dates. Silently fixing dates is not a good idea IMHO. Why can't you just extend the project time frame or generates exports of the global tasks that cover the time frame you need?

Chris

--
TaskJuggler Developer
-- 
To unsubscribe, email: taskjuggler-devel-unsubscribe@suse.com
For additional commands, email: taskjuggler-devel-help@suse.com


This archive was generated by hypermail 2.1.7 : Sun Jun 25 2006 - 12:32:59 CEST