[taskjuggler] Using planbooking

From: Koen Deforche (kdf_at_irule.be)
Date: Tue Nov 05 2002 - 17:14:23 CET

  • Next message: Chris Schlaeger: "Re: [taskjuggler] Using planbooking"
    From: Koen Deforche <kdf@irule.be>
    Date: Tue, 5 Nov 2002 17:14:23 +0100
    Message-Id: <200211051714.23160.kdf@irule.be>
    Subject: [taskjuggler] Using planbooking
    

    Hi all,

    I fail to find a proper syntax for the 'planbooking' feature.

    What I am attempting is something like:
    planbooking 2003-03-02 2003-05-12 qmsch.document

    The task I want to refer to is called 'document', within the task 'qmsch'.
    The project is also called 'qmsch'. I tried lots of different combinations,
    but always got the error:

    Scheduling.tjp:22:Task ID expected

    How can I accomplish this? Will this allow me to reserve a resource
    to do some task while it is on vacation? If not, is there another way
    to do that? The resource is not really on vacation, but caught up in some
    work, but could still do this particular cast in spare time.

    Thanks and regards,
    koen

    -- 
    To unsubscribe, email the address listed in the List-Unsubscribe header
    For additional commands, email: taskjuggler-help@suse.com
    


    This archive was generated by hypermail 2.1.4 : Tue Nov 05 2002 - 17:15:41 CET