Hi all,
I fail to find a proper syntax for the 'planbooking' feature.
What I am attempting is something like:
planbooking 2003-03-02 2003-05-12 qmsch.document
The task I want to refer to is called 'document', within the task 'qmsch'.
The project is also called 'qmsch'. I tried lots of different combinations,
but always got the error:
Scheduling.tjp:22:Task ID expected
How can I accomplish this? Will this allow me to reserve a resource
to do some task while it is on vacation? If not, is there another way
to do that? The resource is not really on vacation, but caught up in some
work, but could still do this particular cast in spare time.
Thanks and regards,
koen