Hi,
On Tuesday 05 November 2002 17:14, Koen Deforche wrote:
> Hi all,
>
> I fail to find a proper syntax for the 'planbooking' feature.
>
> What I am attempting is something like:
> planbooking 2003-03-02 2003-05-12 qmsch.document
The documentation was wrong here. But the above syntax is correct. In some
interim version planbooking had the project ID as 3rd parameter, but that got
dropped. Obviously I didn't correct the documentation before the release.
> The task I want to refer to is called 'document', within the task 'qmsch'.
> The project is also called 'qmsch'. I tried lots of different combinations,
> but always got the error:
>
> Scheduling.tjp:22:Task ID expected
Can you send me a small example that reproduces the problem? You might have
found a bug here. And please send me the version of taskjuggler that you are
using.
> How can I accomplish this? Will this allow me to reserve a resource
> to do some task while it is on vacation? If not, is there another way
> to do that? The resource is not really on vacation, but caught up in some
> work, but could still do this particular cast in spare time.
It probably serves the purpose, but you will get a warning. It's probably a
better idea to assign the resource to another task with higher priority. That
way you let TJ decide about spare time and are sure not to overload the
resource. Assign a flag to this task so that you can hide it in all reports
since it does not matter for the project.
Chris
> Thanks and regards,
> koen
-- KDE 3.0: Conquer your Desktop! http://www.kde.org-- To unsubscribe, email the address listed in the List-Unsubscribe header For additional commands, email: taskjuggler-help@suse.com
This archive was generated by hypermail 2.1.4 : Wed Nov 06 2002 - 14:31:50 CET