Hi,
I am starting to use taskjuggler and I really like it.
Actually I have to schelude a new project , and I am using its data to
practise with taskjuggler.
One of the problems I use to have is , for example , suppose I have two
tasks (A&B) , and the second (B) depends from the first (A) , but supose the
second task can start when the first task reach 50% of realization.
The only way I have to represent it (I think) is to divide the fisrt task in
two tasks (A1&A2) , and make second task (B) depends from the first part (A1)
of the first task (A).
... I don't know it's clear , well the problem is that this happens
habitually and I use to work with a lot of tasks , so I have to divide
too much tasks and the project loose visibility and clarity.
The question is , Does exist an easy way to define such "relative" or
"soft" dependencies with taskjuggler? , and if not , Don't you think it
could be an interesting feature for taskjuggler?
Thanks in advance.
Hgb