From: Chris Schlaeger <cs@suse.de> Date: Mon, 12 May 2003 11:28:06 +0200 Message-Id: <200305121128.07930.cs@suse.de> Subject: Re: [taskjuggler] How to plan weekly meetings/events
On Monday 12 May 2003 10:00, jochen.kilian@philips.com wrote:
> Hi
>
> I use taskjuggler for the first time in a SW project for about 10
> developers.
> In general taskjuggler is working great.
>
> The problem I have is, I do not know, how to plan the weekly meeting for
> the team.
> So I want to have a weekly meeting for 1 hour for the complete team. How
> can I tell this
> taskjuggler.
TaskJuggler cannot handle repeating events right now. This might change in
future versions though. But in your case you are lucky enough that it works
anyway. Weekly repeating events are already possible.
First you need to define a shift with just the meeting hours:
shift weeklyMeeting "Weekly Meeting" {
mon 10:00 - 12:00
tue off
wed off
thu off
fri off
}
Then limit the allocations of the resources to this shift.
task meeting "Weekly Meeting" {
start 2003-05-12
duration 6m
allocate joe
allocate jim
shift weeklyMeeting
}
> Stromerstrasse 5-7 Phone: +49 911 2001 1168
> 90443 Nuremberg Fax : +49 911 2001 1102
^^^^^
Hey that must be around the corner from the old SuSE Headquarter.
Chris
-- KDE 3.1: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Mon May 12 2003 - 11:30:28 CEST