From: Chris Schlaeger (cs_at_suse.de)
Date: Mon May 12 2003 - 20:16:02 CEST
From: Chris Schlaeger <cs@suse.de> Date: Mon, 12 May 2003 20:16:02 +0200 Message-Id: <200305122016.07110.cs@suse.de> Subject: Re: [taskjuggler] Feature request: combine effort and duration
On Monday 12 May 2003 19:32, Holger Karl wrote:
> Hello,
>
> taskjuggler might be a tool that could implement a long-wished-for dream: a
> reasonable combination of effort and duration scheduling :-)
>
> Case in point: frequently, there is a task which is assigned a given man
> power and which also extends over a given duration (adminstration,
> maintenance, etc.) types of tasks.
>
> While the mailing archieve has some hints how to do this, I would be really
> GREAT to be able to combine these two types (essentially, it boils down to
> computing the "load" attribute for the resrouces, I believe).
With "load" you can limit the working hours per day. If you want to control
the hours per week or month, you need to define work hours during which the
resources should be assigned to the task. This is done using the shift
property. See the ShiftPlan example that comes with TaskJuggler.
Chris
-- KDE 3.1: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Mon May 12 2003 - 20:18:26 CEST