Hi,

> We're under a crunch so we will have to work 10 hour days for the next
> couple of months. Even though I specify the working hours for my resources
> (my staff) to be 10 hours long, it only seems to allocate 8 hours on a
> single day. How do I fix this?

I think you should set the

 dailyworkinghours
which is a property of the project.

See
http://www.taskjuggler.org/manual/project.html#PROJECT_DAILYWORKINGHOURS

Rgds,

Klaas

-- 