> We're under a crunch so we will have to work 10 hour days for the next
> couple of months. Even though I specify the working hours for my resources
> (my staff) to be 10 hours long, it only seems to allocate 8 hours on a
> single day. How do I fix this?
I think you should set the
dailyworkinghours
which is a property of the project.
See
http://www.taskjuggler.org/manual/project.html#PROJECT_DAILYWORKINGHOURS
Rgds,
Klaas
--