Hello!
I try to use taskjuggler to track computer network building project. And
I've got following question - how can I express in taskjuggler use of
resources like cable, switches, racks etc. etc.? Ie. I'd like to assign
to some tasks information, that to do it I need 10 24-port switches and
1 km of UTP cable. Then I'd like to generate report, where I can see how
many switches, cable etc. I need ie. in monday, or in next week - just
to improve ordering policy. For now I use for this purpose accounts, but
this is a little inconvinient - ie. I can have only one account defined
per tasks, I cannot see account report per task, I cannont export this
accounts. Any ideas?