From: Chris Schlaeger (cs_at_suse.de)
Date: Wed Oct 29 2003 - 20:52:24 CET
From: Chris Schlaeger <cs@suse.de> Date: Wed, 29 Oct 2003 20:52:24 +0100 Message-Id: <200310292052.26075.cs@suse.de> Subject: Re: [taskjuggler] can I use "materials" in taskjuggler?
Hi,
currently TaskJuggler has no support for consumable (or renewable) resources.
I have some vague plans to support this in the future, but currently you
can't do this. Accounts are really only meant for money.
Chris
On Wednesday 29 October 2003 16:02, Grzegorz MarszaÅek³ek wrote:
> Hello!
>
> I try to use taskjuggler to track computer network building project. And
> I've got following question - how can I express in taskjuggler use of
> resources like cable, switches, racks etc. etc.? Ie. I'd like to assign
> to some tasks information, that to do it I need 10 24-port switches and
> 1 km of UTP cable. Then I'd like to generate report, where I can see how
> many switches, cable etc. I need ie. in monday, or in next week - just
> to improve ordering policy. For now I use for this purpose accounts, but
> this is a little inconvinient - ie. I can have only one account defined
> per tasks, I cannot see account report per task, I cannont export this
> accounts. Any ideas?
>
> Best regards
>
> --
> Grzegorz MarszaÅekÅek <gmarszalek@biuro.lanet.wroc.net>
> LANet Sp. z o.o.
-- KDE 3.1: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Wed Oct 29 2003 - 20:52:48 CET