[taskjuggler] empty resources for finished tasks

From: Michal Vitecek (fuf_at_interactive-1.com)
Date: Wed Dec 01 2004 - 20:05:18 CET


Date: Wed, 1 Dec 2004 20:05:18 +0100
From: Michal Vitecek <fuf@interactive-1.com>
Message-ID: <20041201190517.GK7593@foof.i3.cz>
Subject: [taskjuggler] empty resources for finished tasks


 hello everyone,

 i'm trying to use taskjuggler for my project and am struggling with
 some problems i'm unable to solve.

 1) when a task is finished, it most of the time has no resources
    allocated to it, ie.:

    task task1 "task1" {
        allocate resource1
        complete 100
        start 2004-12-01-14:00
        length 2h
        end 2004-12-01-16:00
    }

    with this i was expecting that 2 hours will be taken from the
    resource1's availability and that the resource will be allocated to
    the task. however in the status report HTML, no resource is shown
    for the task :/

 2) maybe it's because i'm not using taskjuggler correctly. how can i
    specify exactly that a task was started/finished at a certain time
    and that some resource was working on it? i'd like to compare my
    planned values with reality values (i have two scenarios).

        thank you,

-- 
		fuf		(fuf@mageo.cz)
-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


This archive was generated by hypermail 2.1.7 : Wed Dec 01 2004 - 20:05:39 CET