hello everyone,
i'm trying to use taskjuggler for my project and am struggling with
some problems i'm unable to solve.
1) when a task is finished, it most of the time has no resources
allocated to it, ie.:
task task1 "task1" {
allocate resource1
complete 100
start 2004-12-01-14:00
length 2h
end 2004-12-01-16:00
}
with this i was expecting that 2 hours will be taken from the
resource1's availability and that the resource will be allocated to
the task. however in the status report HTML, no resource is shown
for the task :/
2) maybe it's because i'm not using taskjuggler correctly. how can i
specify exactly that a task was started/finished at a certain time
and that some resource was working on it? i'd like to compare my
planned values with reality values (i have two scenarios).
thank you,