On Tuesday 16 March 2004 18:54, g.kroling@swipnet.se wrote:
> HI,
> Thanks for your efforts. Works very well. But I want to force a task to be
> done during one single day ( casting a concrete beam for example ) but it
> get spread out over two days. Is that covered in a faq or so?
Can you send some example tasks and the scheduling result that illustrates
what you are trying to do?
Chris
>