[taskjuggler] Shared resource not taking hours from effort

From: Hindrik Hettema (h_hettema_at_gmx.net)
Date: Thu Sep 16 2004 - 11:31:37 CEST


Date: Thu, 16 Sep 2004 11:31:37 +0200 (MEST)
From: "Hindrik Hettema" <h_hettema@gmx.net>
Message-ID: <4697.1095327097@www25.gmx.net>
Subject: [taskjuggler] Shared resource not taking hours from effort

Hello,

I have the following problem: I am planning a project with several
acceptance tests as task. These acceptance tests each have a certain
effort defined, and with each of these tests one official from the customer
has to be present.

How can I in taskjuggler arrange that the official is modelled (so
the tests do not overlap) but not get the official book any hours
on the hours specified in effort for that task? Is that possible?

Example: task aap "aap" { effort 8h allocate jan, official { mandatory } }
         task noot "noot" { effort 16h allocate piet, official { mandatory }
}

These tasks must now not be scheduled in parallel, the official cannot be in
two places at the same time.

Any help is appreciated,

Kind regards,

Hindrik Hettema

-- 
Supergünstige DSL-Tarife + WLAN-Router für 0,- EUR*
Jetzt zu GMX wechseln und sparen http://www.gmx.net/de/go/dsl
-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


This archive was generated by hypermail 2.1.7 : Thu Sep 16 2004 - 11:33:43 CEST