[taskjuggler] Re: Resoource juggling

david_at_anon.nu
Date: Thu Sep 30 2004 - 12:41:40 CEST


Message-ID: <415BE2E4.9000204@anon.nu>
Date: Thu, 30 Sep 2004 11:41:40 +0100
From: david@anon.nu
Subject: [taskjuggler] Re: Resoource juggling

Max Hofer wrote:

> you have to declare the room as mandatory. so you get 4 tasks,

But if all the guests are needed to be there - then I guess they are
mandatory as well?

> each allocating
>
>one of the persons and the mandatory room resource (which is only available
>on weekends).
>
>
OK - so I'll go ahead and try. The hard bit I've got to do is to
translate the timetables of the people into something taskjuggler
understands. I think the time tables will be in iCal format. I have not
found any examples of complicated resource limit / vacation use - I am
thinking of using the "vacation" keyword and generating a long list of
them for each resource based on their time tables.

Does this make sense? has anyone else tried something like this?

>make sure to use "duration" and not "effort" for the tasks.
>
Thanks for the help.

-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


This archive was generated by hypermail 2.1.7 : Thu Sep 30 2004 - 12:44:07 CEST