Re: [taskjuggler] Re: Resoource juggling

From: Joachim Werner (joe_at_suse.de)
Date: Thu Sep 30 2004 - 13:47:49 CEST


Message-ID: <415BF265.4050504@suse.de>
Date: Thu, 30 Sep 2004 13:47:49 +0200
From: Joachim Werner <joe@suse.de>
Subject: Re: [taskjuggler] Re: Resoource juggling

Hi!

I haven't seen the original posting for this. Did it go to the list?

david@anon.nu schrieb:
> OK - so I'll go ahead and try. The hard bit I've got to do is to
> translate the timetables of the people into something taskjuggler
> understands. I think the time tables will be in iCal format. I have not
> found any examples of complicated resource limit / vacation use - I am
> thinking of using the "vacation" keyword and generating a long list of
> them for each resource based on their time tables.
> Does this make sense? has anyone else tried something like this?

Here at SUSE we use auto-generated vacation entries, yes. It shouldn't
be that hard to do. I don't know what you want to do exactly, but if you
let some script generate the vacation entries from iCal and "include"
the resulting file into your master file this should work fine.

Remember that you don't have to put the vacation entries into the
resource's resource definition, but can do it anywhere in the script or
in an include if you use

supplement resource name_of_resource { ... }

Cheers

Joachim

-- 
Joachim Werner
SUSE RD-TPM
-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


This archive was generated by hypermail 2.1.7 : Thu Sep 30 2004 - 13:51:18 CEST