[taskjuggler] Re: Unbreakable tasks

From: Chris Schlaeger (cs_at_suse.de)
Date: Fri Aug 19 2005 - 20:09:24 CEST


From: Chris Schlaeger <cs@suse.de>
Message-Id: <20050819180924.54DEC2730E5A@einstein.suse.de>
Date: Fri, 19 Aug 2005 20:09:24 +0200 (CEST)
Subject: [taskjuggler] Re: Unbreakable tasks


Looking at your project here is what should happen:

mpe9d starts on the 8th with OS assigned full time.
On the 16th mpe9e starts with just AM assigned. Since it has a lower priority it does not draw OS away from mpe9d.
On the 17th mpe9d is finished and OS joins AM on mpe9e.

If you get a different result, then your resources are probably taken away by higher priority tasks.

To make a task always get the resources you can use priority 1000. But it only works if there is no competing prio 1000 tasks.

Chris

--
TaskJuggler Developer
-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com