I want to interleave small project inside large project: actually i'm completly locket with the following sample because taskjuggler want to put the small project before or after the large project. what is the best way to do that ?
The result is:
'plan' end time of task 'smallproject' is too late
Date is: 2006-02-09-18:00:00-CET
Limit is: 2006-01-15-00:00:00-CET
project yourID "Your Project" "1.0" 2005-11-01 2006-12-30
{
timeformat "%Y-%m-%d"
currency "EUR"
scenario plan "Plan" { projection { strict } }
now 2005-12-01
}
resource dev "Developers"
{
resource dev1 "dev1"
resource dev2 "dev2"
resource dev3 "dev3"
}
task bigproject "Big Project"
{
task spec "Specification"
{
effort 20d
allocate dev1
depends !deliveries.start
}
task software "Software Development"
{
depends !spec
effort 20d
allocate dev1, dev2
}
task deliveries "Milestones"
{
task start "Projectstart"
{
milestone
start 2005-12-16
}
task done "Ship Product to customer"
{
milestone
maxend 2006-06-15
depends !!software
}
}
}
task smallproject "Small Project"
{
start 2005-12-16
effort 10d
allocate dev1
maxend 2006-01-15
}
taskreport "Project Overview"
{
columns start, end, effort, duration, completed, cost, revenue, chart
}
resourcereport "Resource Usage"
{
columns effort, freeload, utilization, rate, chart
hideresource 0
}