hi,

My problem is to define a meaningful enddate for a project.
I thought tj can calculate it but this seems to be wrong.
Of course i can define an enddate far in the future, but
this has some disadvantages. e.g. when i print out the report.

The workaround i do at the moment is to run tj 2 times.
Before first run i define in an enddate far in the future.
After first execution of tj i grab the scheduled endate of the maintask,
and use it as project enddate for the 2. execution.

Is their a better way?

karl

-- 