It's ok to set an end date far in the future. It will increase memory consumption and in certain cases runtime though. So don't set it too far in the future. Usually the project time frame stabilizes after the initial planning phase and rarely needs to be adjusted.

Chris

--
TaskJuggler Developer
-- 