On Tuesday 01 February 2005 21:26, Nigel.Brown@qml.com.au wrote:
> I'm looking at how to structure a project definition so that tasks are only
> scheduled when an income account is positive enough -
>
> eg if a client makes periodic payments that go into the project income
> account and tasks are scheduled such that if the project account is
>
> depleted by tasks then the next task can't begin until the next scheduled
> payment takes the account positive enough -
>
> can taskjuggler do this?
Interesting concept ;)
The TJ scheduler does not operate chronologically. So the accounting can only
be done, when the complete project has been scheduled.
But you can use the P&L account reports to find out, when you are running out
of cash and then manually adjust the start times accordingly.
Chris
>
> Regards
>
> Nigel