Re: [taskjuggler] schedule by cash availability?

From: Chris Schlaeger (cs_at_suse.de)
Date: Wed Feb 02 2005 - 06:48:54 CET


From: Chris Schlaeger <cs@suse.de>
Date: Tue, 1 Feb 2005 22:48:54 -0700
Message-Id: <200502012248.56398.cs@suse.de>
Subject: Re: [taskjuggler] schedule by cash availability?


On Tuesday 01 February 2005 21:26, Nigel.Brown@qml.com.au wrote:
> I'm looking at how to structure a project definition so that tasks are only
> scheduled when an income account is positive enough -
>
> eg if a client makes periodic payments that go into the project income
> account and tasks are scheduled such that if the project account is
>
> depleted by tasks then the next task can't begin until the next scheduled
> payment takes the account positive enough -
>
> can taskjuggler do this?

Interesting concept ;)

The TJ scheduler does not operate chronologically. So the accounting can only
be done, when the complete project has been scheduled.

But you can use the P&L account reports to find out, when you are running out
of cash and then manually adjust the start times accordingly.

Chris

>
> Regards
>
> Nigel

-- 
KDE 3.3: Conquer your Enterprise Desktop!  See http://www.kde.org!
GPG Key: 1024D/0500838B  A5FE C051 2AFC 9A14 768A  5125 5829 5750 0500 838B




This archive was generated by hypermail 2.1.7 : Wed Feb 02 2005 - 06:49:57 CET