From: Chris Schlaeger (cs_at_suse.de)
Date: Thu Feb 03 2005 - 00:46:07 CET
From: Chris Schlaeger <cs@suse.de> Date: Wed, 2 Feb 2005 16:46:07 -0700 Message-Id: <200502021646.08772.cs@suse.de> Subject: Re: [taskjuggler] schedule by cash availability?
On Wednesday 02 February 2005 16:22, Nigel.Brown@qml.com.au wrote:
> > Yes, see http://www.taskjuggler.org/manual-cvs/property_limits.html. That
> > should do the trick.
>
> Thinking about it the limit I really need is probably projectmax - does
> just putting a duration in the braces eg limit { 4d } do that? With
> monthlymax etc the total availability of the resource varies with project
> duration.
The projectmax you are looking for is called 'effort'. It limits the effort
for the whole task so it's a task attribute, not an allocation attribute. The
other limits throttle the resource load over the specified periods of time.
Chris
-- KDE 3.3: Conquer your Enterprise Desktop! See http://www.kde.org! GPG Key: 1024D/0500838B A5FE C051 2AFC 9A14 768A 5125 5829 5750 0500 838B
This archive was generated by hypermail 2.1.7 : Thu Feb 03 2005 - 00:46:13 CET