Hi there,
using ktjview2 I discovered a deviation in the scheduling of task
presented in the GUI and the schedule presented in the html and xml
files. E.g., there is a task named XXX.Dev.GUI.Design and according to
the Tasks-view it is scheduled
XXX.Dev.GUI.Design GUI Design 15.2.2005 16:00 16.2.2005 15:59 3 ....
while the XML-file produced by taskjuggler says:
<task projectId="XXX" milestone="0" asapScheduling="1"
priority="1000" id="XXX.Dev.GUI.Design" name="GUI Design" >
<depends>XXX.Dev.Core.GuiInterf</depends>
<depends>XXX.Dev.GUI.Basics</depends>
<taskScenario complete="90" effort="2" scheduled="1"
scenarioId="plan" >
<start humanReadable="2005-01-31" >1107187200</start>
<end humanReadable="2005-02-02" >1107360000</end>
</taskScenario>
(The snippets above are part of a test project which is already quite
complex. Thus I avoided to post the complete project source)
Question: Do ktjview2 and taskjuggler make use of different scheduling
algorithms?
Thank you,
Uli
-- Ulrich Hammel Vice Managing Director German Operations NuTech Solutions GmbH Martin-Schmeißer-Weg 15 44227 Dortmund Germany Phone: +49 231 72546320 Fax: +49 231 72546329 Mobil: +49 173 5666359 mailto: hammel@nutechsolutions.de www.nutechsolutions.de Adaptive Business Solutions -- To unsubscribe, email the address listed in the List-Unsubscribe header For additional commands, email: taskjuggler-help@suse.com