Hi Anders,

On Tuesday 04 January 2005 17:56, Anders Kaestner wrote:
> Hello,
>
> I'd like to know if it is possible to manage/schedule equipment usage, such
> as computers, parallel to human resources.
> If I only allocate the computer as a common resource will the human work
> time be reduced by the computer time and that is not true...

yes, this has been fixed already, but not yet officially released. If you use
the CVS snapshots, you can set efficiency to 0 and your equipment is no
longer doing human work.

> so what I (think I) need is a second effort counter (e.g. equip_effort)
> that runs parallel to the usual effort counter and the task is only
> finished when the longest effort time (human_resource_effort_time or
> equipment_resource_effort_time) is reached. This could maybe be even more
> generalized. Something like independent workgroups that can work in
> parallel.

I've been thinking about this for a while already, but I haven't found a
generalization that pleased me. But I've stopped working on this for the time
being as I focused my time on the IDE/GUI recently. I will definitely come
back to this issue again. But setting efficiency to 0 is a good solution for
the moment.

Chris

>
> /Anders

-- 
KDE 3.3: Conquer your Enterprise Desktop!  See http://www.kde.org!
GPG Key: 1024D/0500838B  A5FE C051 2AFC 9A14 768A  5125 5829 5750 0500 838B




This archive was generated by hypermail 2.1.7 : Sun Jan 09 2005 - 12:38:01 CET