[taskjuggler] how do I let TJ allocate one person from a pool for a task?

From: Caspar Terheggen (caspar_at_tunix.nl)
Date: Mon Jan 31 2005 - 17:13:20 CET


Message-Id: <200501311613.j0VGDKcX015688@thetix.tunix.nl>
Date: Mon, 31 Jan 2005 17:13:20 +0100
From: Caspar Terheggen <caspar@tunix.nl>
Subject: [taskjuggler] how do I let TJ allocate one person from a pool for a task?


Hi,

I am using taskjuggler v2.0.1. I have a question.

If I specify:

        task foo "foo" {
                effort 3d
                allocate george {
                        alternative john
                }
        }

then it might happen that taskjuggler will allocate George for 1.8 day
and John for 1.2 day for this task. However I would like taskjuggler
to pick one of these people and stick with it. This is because these
tasks can be performed by either one of them, but once someone is
working on it, it is not possible for someone else to take over. Is
there a way to do this?

cheers,
Caspar

-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com