Re: [taskjuggler] plan and ... what happens

From: Max Hofer (max.hofer_at_apus.co.at)
Date: Mon Jun 06 2005 - 09:18:03 CEST


From: Max Hofer <max.hofer@apus.co.at>
Date: Mon, 6 Jun 2005 09:18:03 +0200
Message-Id: <200506060918.03170.max.hofer@apus.co.at>
Subject: Re: [taskjuggler] plan and ... what happens

On Monday 06 June 2005 07:51, nino wrote:
> This sounds like two different scennarios would be the way to go, but... I
> would like to have a plan scennario and a independent scennario
> (effective), where I can keep track on the actual time spent on the tasks.
> The second scennario is ment to be used for the calculation of the money
> used for the individual steps.
>
> But since the effecive scennario is nested in the plan scennario I cant get
> the timeline decoupled from eachother...
What about using the "supplement" keyword?

With it you can add the "realized" scenario (for the calculations) in a
separate file and use "include" to include it.

If you are using an external tool to track the hours spent on the project you
could write a tool, which generates the "realized" scenario file.

The biggest problem i see doing this, is when you change the project
structure. You would need to change the "realized" scenario in the same way.

-- 
Max Hofer
APUS Software G.m.b.H.
A-8074 Raaba, Bahnhofstraße 1/1
T| +43 316 401629 11
F| +43 316 401629 9
W| www.apus.co.at
E| max.hofer@apus.co.at
-- 
To unsubscribe, email the address listed in the List-Unsubscribe header
For additional commands, email: taskjuggler-help@suse.com


This archive was generated by hypermail 2.1.7 : Mon Jun 06 2005 - 09:18:13 CEST