On Monday 06 June 2005 07:51, nino wrote:
> This sounds like two different scennarios would be the way to go, but... I
> would like to have a plan scennario and a independent scennario
> (effective), where I can keep track on the actual time spent on the tasks.
> The second scennario is ment to be used for the calculation of the money
> used for the individual steps.
>
> But since the effecive scennario is nested in the plan scennario I cant get
> the timeline decoupled from eachother...
What about using the "supplement" keyword?
With it you can add the "realized" scenario (for the calculations) in a
separate file and use "include" to include it.
If you are using an external tool to track the hours spent on the project you
could write a tool, which generates the "realized" scenario file.
The biggest problem i see doing this, is when you change the project
structure. You would need to change the "realized" scenario in the same way.