From: Chris Schlaeger <cs@kde.org> Message-ID: <19ef.4415caec@www.taskjuggler.org> Date: Mon, 13 Mar 2006 20:41:33 +0100 (CET) Subject: [taskjuggler] Re: Problem in schedule - with Large projects with many top-level tasks
Similar bug like the first one. But this time it was in the pre-scheduling critical path analyzer. It's fixed now. Please try the current SVN snapshot again.